High Holborn

Direct for PQS

  • -Replacement of Dry Air Coolers (2 V Bank Type) in sequence whilst keeping cooling available to all areas (Circuit by circuit);
  • -Crane lift of the main plant overnight works and full weekend for change-over to enable full cooling availability by Monday morning;
  • -Plant base supports (Steel works);
  • -AHU Refurbishment and full ductwork cleaning of existing system (Night works);
  • -Refurbishment of existing Chillers;
  • -Replacement of existing Side stream filtration units;
  • -Remedial works to base build fan coil units and valves.